NAME: | Rohan Gyawali | ||||
PROJECT TITLE: | Rehabilitation of Parkinson patients by the help of wearable sensors | ||||
WEEK NO: | 10 | DATE:29/05/2020 | |||
PLANNING | finishing final project and presentation | ||||
MILESTONE: | PLANNED: | ACTUAL: | COMMENT: | ||
Final project has been finished and presentation as well | 15/05/2020. | 29/05/2020 | prsesntation and presentation will be submitted on due date. | ||
ISSUES | |||||
DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) | ||
Finished final report and presentation from Screencast-O-matic for recording presentation | 15/04/2020 | 29/05/2020. | Y |