Week 6 – Progress Report

WEEKLY PROGRESS REPORT

 

NAME Ranidu Thiwanka
PROJECT TITLE Integrated block-chain technology in health care services and cloud-based security and privacy
WEEK NO 6 DATE 19 April 2021
PLANNING
MILESTONE PLANNED ACTUAL COMMENT
Annotated Bibliography and Literature Review 100% – 3 days 100% – 6 days All the selected papers were cross referenced to extract the essence from all the papers and create taxonomies. Forward referencing, backward referencing, and finding papers from famous authors in the field was used in finding other papers related to the selected topic. 
Reflective Analysis  100% – 1 day 100% – 1 day The reflective analysis was written after analysing all the 12 research papers
ISSUES
DESCRIPTION DATE ACTION/RESULTS FINISHED
The time allocated for the literature review at first was insufficient. 15/04/2021 Added three more days on the literature review than previously planned to complete a thorough review.  Issue solved and completed the task

 