    Planning:
    Milestone Planned Actual Comment
    To complete the component table of review system. First analyse the main components of review system and then describing the common instances and attributes. Components of component table has been found and working to analyse the actual data from those articles. I found various common evaluation metrics which contribute to measure performance.
    Issues
    Description Date Action Finished
    Data sets are several and different from each other. 23/04/2021 Only common and usable data sets has been considered. Yes