Week 12

NAME: Niren Panchal
PROJECT TITLE: Distributed Database Technologies using Blockchain
WEEK NO: 12 DATE: 30/05/2021
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT:
Send the study paper and the presentation. To present the presentation and the study. I had to make slight adjustments to the submission slides and to the study paper. I have helped to make the study paper portions available online.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
The literature review table in the study covered problems that clarified the reader and did not make the document long. 30/05/2021 Help me do research paper pieces online. Y

 

Week 11

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies
WEEK NO: 11 DATE: 29/05/2021
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT:
Complete the presentation updates. End your presentation. Small modifications to the presentation slides were necessary. Help with the lectures and topics of the library support.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Some of the components of the research submission had problems. 29/05/2021 Help with the lectures and topics of the library support. Y

 

Week 10

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies using Blockchain
WEEK NO: 10 DATE: 18/05/2021
PLANNING The results of the investigation were analyzed.
MILESTONE: PLANNED: ACTUAL: COMMENT:
The project results have been determined. The project results.Complete writing the research paper. The assessment of the outcomes and the results. The research outcomes were assessed and examined Project achievements analysed
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
I have had problems with some of the research paper components. 18/05/2021 I received assistance from the study support session, and similar peer reviews to meet the acceptable standard from my research paper. Y

 

Week 9

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
WEEK NO: 09 DATE: 12/05/2021
PLANNING Risk analysis carried out in the current research
MILESTONE: PLANNED: ACTUAL: COMMENT:
The dangers will be assessed throughout the research activity. The determination of hazards in the project done The dangers will be assessed in 3 days Online searches have helped resolve various problems.
ISSUES Risks evolve in a timely manner
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
The risks of study according to the research strategy have been assessed 12/05/2021 The answer for risk reduction has been identified Y

 

Week 8

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
WEEK NO: 08 DATE: 05/05/2021
PLANNING Ethical problems were analyzed in the research
MILESTONE: PLANNED: ACTUAL: COMMENT:
Comparative analysis of ethical research actions. Analyzing and determining ethical dilemmas. Identify successfully the ethical problems Studied ethical consideration
ISSUES The ethical problems relevant to the investigation were identified
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Ethical issues have been identified successfully. 05/05/2021 The study of the ethical problems was expected in the research. Y

 

Week 7

NAME: Niren Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
WEEK NO: 07 DATE: 21/04/2021
PLANNING Research analysis used for research Analysis
MILESTONE: PLANNED: ACTUAL: COMMENT:
The method of research will be examined for research ideas Research technique collection within 3 days The project will be done within 3 days in accordance with the schedule Online searches helped to overcome different difficulties.
ISSUES The schedule and costs have been planned.
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
The team members effectively collected the notion of the research approach. 21/04/2021 Therefore, the research methodologies were studied in full. Y

 

Week 6

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
WEEK NO: 05 DATE: 11/04/2021
PLANNING Methods and procedures for data collection are examined.
MILESTONE: PLANNED: ACTUAL: COMMENT:
The choice of data collection methods and techniques The analysis of what procedures and procedures are used for data collection methods will be performed. After reading through research papers I analyze the methods and codes I started with developing the code for the classifier and the pre-processing codes. Before the end of the two days, the data gathering procedures were determined..
ISSUES More resources are required to predict data collection strategies.
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Various useful study findings will be obtained. 11/04/2021 The data-gathering technique analysis can lead to the appropriate findings Y

Week 5

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
05 DATE: 06/04/2021
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT:
The efficient and appropriate data collection approach is chosen for the investigation. The data collection approach for gathering successful research ideas was reviewed. Methods for collecting data have been identified in accordance with the plan. Approaches in the research papers and online references helped me to do the development.
ISSUES Identified the most effective data collection methods
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
For reviewing a research work, I used data collection methods. 6/04/2021 The methods of data gathering chosen can help the research to obtain ideas. Y

Week 4

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
WEEK NO: 04 DATE: 28/03/2021
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT:
Finalizing assignment 2 and submission of assignment 2. Planned to accomplish task 2 and to use the indicated approaches. I examine the methods and conclude my method and conclude my task after going through research papers 2. The research paper methodology area let me identify their approaches and offered me a notion of my method.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
The dataset I earlier used was not suited as it consisted of Spanish reviews as well. 28/03/2021 I choose to utilize a new dataset with English terms only. Y

Week 3

NAME: Niren Jitendrabhai Panchal
PROJECT TITLE: Distributed Database Technologies Using Blockchain
WEEK NO: 03 DATE: 21/03/2021
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT:
Finalizing the framework for the project and finding a relevant database It was planned to find a suitable framework for the project as well as a suitable database. I evaluated the frameworks of their projects after reading research articles and drafted one for my own project. I looked for a database that would be appropriate for the project. The method section in the research papers assisted me in locating the framework, and the discovered database must be reviewed with the instructor before it can be finalized.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
By reading the approaches, I have learned that both classification approaches can’t be managed. 21/03/2021 For the capstone assignment, I decided just to use one classification category. Y

 