Project – Plan and Proposal

WBS- Work Break Down Structure

 ID  Task Name  Duration  Start  Finish
1 Initiation phase 4 wks  Mon 3/02/20  Fri 3/27/20
a.     Identification of the topic 1 wk  Mon 3/02/20  Fri 3/06/20
b.     Determining issues 1 wk  Mon 3/09/20  Fri 3/13/20
c.     Elaborating objectives and aims of the project 1 wk  Mon 3/16/20  Fri 3/20/20
d.     Creating questions for research plan 1 wk  Mon 3/23/20  Fri 3/27/20
2 Planning phase 3 wks  Mon 4/13/20  Fri 5/01/20
a.     Making prepration for project plan 0.6 wks  Mon 4/13/20  Wed 4/15/20
b.     Getting approval from higher management of the organization 0.4 wks  Thu 4/16/20  Fri 4/17/20
c.     Focussing on research question 1 wk  Mon 4/20/20  Fri 4/24/20
d.     Selection of research  methodology 1 wk  Mon 4/27/20  Fri 5/01/20
3 Execution phase 3 wks  Mon 5/04/20  Fri 5/22/20
a.     Identifying journal articles 1 wk  Mon 5/04/20  Fri 5/08/20
b.     Reviewing articles 1 wk  Mon 5/11/20  Fri 5/15/20
c.     Creating annotated bibliography 1 wk  Mon 5/18/20  Fri 5/22/20
4 Closure phase 1 wk  Mon 5/25/20  Fri 5/29/20
a.     Preparing for presentation 0.8 wks  Mon 6/01/20  Thu 6/04/20
b.     Presentation on big data 0.2 wks  Fri 6/08/20  Fri 6/08/20