Project Plan
Work Breakdown Structure (WBS) | ||||
Sprint # | 01 | Project Name | Research on How an augmented reality changed the decision of the online purchasing | |
Start Date | 20/07/2020 | Project Number | P4354 | |
End Date | 06/10/2020 | Project Manager | Harsha Dilup Kumara | |
Releases |
|
Prepared By | Harsha Dilup Kumara | |
WBS | Task Name | Start Date | ||
1 | Initiating | |||
1.1 | Finding a suitable capstone research project | 20/07/20 | ||
1.2 | Write a project abstract | 21/07/20 | ||
1.3 | Setting up a project blog for documentation | 23/07/20 | ||
1.4 | Update weekly progress report – week 2 | 25/07/20 | ||
1.5 | Finding existing literature based on the field of augmented reality | 26/07/20 | ||
1.6 | Develop a research topic from the investigation | 26/07/20 | ||
1.7 | Saving research journal using Zotero | 27/08/20 | ||
2 | Planning | |||
2.1 | Develop a project proposal | 03/08/20 | ||
2.2 | Creating a methodology | 04/08/20 | ||
2.3 | Project Plan, WBS and Gantt Chart | 06/08/20 | ||
2.4 | Update weekly progress report – week 3 | 10/08/20 | ||
3 | Execution Phase | |||
3.1 | Primary and Secondary Data Collection | 10/08/20 | ||
3.2 | Data Analysis | 11/08/20 | ||
3.3 | Writing ethics of qualitative methods | 12/08/20 | ||
3.4 | Writing ethics of quantitative methods | 14/08/20 | ||
3.5 | Writing annotations using endnote | 15/08/20 | ||
3.6 | Update weekly progress report – week 4 | 17/08/20 | ||
3.7 | Constructing Annotated Bibliography for Literature Review | 18/08/20 | ||
3.8 | Writing the journal synopsis paper | 24/08/20 | ||
3.9 | Update weekly progress report – week 5 | 17/08/20 | ||
3.10 | Update weekly progress report – week 6 | 24/08/20 | ||
4 | Designing and development of a try-on APP | |||
4.1 | Designing unity 3D model for try-on app | 25/08/20 | ||
4.2 | UI design for the customizing 3D model | 26/08/20 | ||
4.3 | Design Image target and adding to Vuforia engine target manager | 28/08/20 | ||
4.4 | Integrating 3D model to Unity Engine | 31/08/20 | ||
4.5 | Adding a 3D model to Vuforia image target | 01/09/20 | ||
4.6 | Adding reflection and AI to the 3D model | 04/09/20 | ||
4.7 | Testing AR try-on APP | 06/09/20 | ||
5 | Hand-over and closeout | |||
5.1 | Planning the final project report | 07/09/20 | ||
5.2 | Planning project presentation | 14/09/20 | ||
5.3 | Final project presentation | 06/10/20 | ||
5.4 | Update weekly progress report – week 7 | 06/10/20 | ||