Weekly Report | ||||
Name | Salil | |||
Project Title | Containers or Virtualisation ? Why not both ! | |||
Week number | 11—> (10/05/21 – 18/05/21) | |||
Milestone | Planned Completion | Actual Completion | Comments | |
1 | A4- Final report and presentation | 28/05/2021 | I have had to request for an extension of 5 days. | Working on the last assignment for this subject |
2 | A4 Task 1 completed. | 28/05/2021 | I have had to request for an extension of 5 days. | A4 T1 is within the designated word limit |
3 | Commence A4 T2 | 28/05/2021 | I have had to request for an extension of 5 days. | |
Issues | ||||
Description | Date | Action/Results | Finished (Y/N) | |
Formatting A4 Task1 in IEEE format | 28/05/2021 | Work in progress | N | |