May 16

Weekly Reports

Weekly Progress Report  01

NAME : CHIMI DORJI
PROJECT TITLE: Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 2 DATE: 18/03/2020
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
1.     Choose Capstone project title and write an abstract

2.     Create a Blog

18/03/2020 Completed

 

 

Completed

I choose to learn about Edge Computing and IoT Application and Devices

 

Created the blog and the basic menu

ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Selecting the topic on Edge Computing and IoT Applications without having any prior understanding of Edge or IoT 18/03/2020 Read and check on the Y(incomplete )

Weekly Progress Report  02

NAME : CHIMI DORJI
PROJECT TITLE: Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 3 DATE:23/03/2020
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
1.     Project Proposal

2.     Project Planning

 23/03/2020

 

05/04/2020 Had to literature review and research though multiple papers to come up with the project proposal

WBS, Gantt chart and Risk Analysis was done in this section

ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Understanding how to breakdown work and designing and understating Gantt chart and Risk Analysis. 23/03/2020 Read and watched tutorials online N

 

Weekly Progress Report  03

NAME : CHIMI DORJI
PROJECT TITLE:  Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 4 DATE:  22/04/2020
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
1.     Project Proposal and Project Planning Submission 05/04/2020 22/04/2020 After planning and Proposal, the report needed to be submitted vis EAST. Due to the current situation, was unable to make it on the specified due date and had to request for an extension.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Getting down to the desired/required Plagiarism rate of less than 20 % 22/04/2020 Citations and referencing work Y

Weekly Progress Report  04

NAME : CHIMI DORJI
PROJECT TITLE: Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 5 DATE: 23/04/2020
I started refining the Resources for the capstone project.
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
1.     Annotated Bibliography: Find and Refine at least 14 Relevant papers for your topic 23/04/2020 23/04/2020

 

 

 

 Refining the search result into manageable size was rewarding and limiting to 12 was challenging.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Selecting the topic on Time-Critical IoT And Edge computing without having any prior understanding 23/04/2020 Read about blockchain Y (incomplete )

Weekly Progress Report  05

NAME : CHIMI DORJI
PROJECT TITLE: Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 6 DATE: 30/04/20
The week was spent on reviewing some articles which were collected during the previous week and started to filter it down to manageable number by using Boolean connectors
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Searched for relevant articles got a hit of more than 30000 article and tried to bring down to 20 30/04/2020 03/05/2020

 

 

Some articles were not free so I had to skip those.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Filtering then by date, relevance and keyword was hard to sync

 

 

03/05/2020

 

Skimmed through their abstract to see their relevance. Y

Weekly Progress Report  06

NAME : CHIMI DORJI
PROJECT TITLE: Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 7 DATE: 04/05/2020
With enough literature to refer, I started to write the Annotated Bibliography, and some articles though relevant were removed as others were more relevant.
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Started writing the bibliography 04/05/2020 04/05/2020 I started to write the Annotated bibliography with the resources downloaded and trying to get it on time.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Most article seem to have the similar introductions 04/05/2020 On going Y

Weekly Progress Report  07

NAME : CHIMI DORJI
PROJECT TITLE : Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 8 DATE: 10/05/2020
Finished and submitted the Annotated bibliography
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Wrote the annotated bibliography on 12 articles 10/05/2020 10/05/2020 Though requesting for an extension anticipating that I might not complete it on time but managed to squeeze it in on time.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Took more time than expected as most journals seem to talk about the same concept 10/05/2020 Completed Y

Weekly Progress Report  08

NAME : CHIMI DORJI
PROJECT TITLE  : Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 9 DATE: 13/05/2020
Revisited the Journals downloaded and started to edit the Final Report
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Working on the final report and trying to proof read what has been written so far 11/05/2020 13/05/2020 Some articles were not free so had to skip those. Still having troubling managing time with home school two children under the age of 9. Finally kick-started Final report and hope to keep moving forward.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Worried about the choice of topic so thought investigating rather then going for a definite goal. 13/05/2020 Taken Ongoing

Weekly Progress Report  9

NAME : CHIMI DORJI
PROJECT TITLE  : Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 10 DATE:  16/05/2020
Updated the blog and posted it online, as all the weekly report was stored on my desktop and worked on the Final report.
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Preparing for the Final Report and Updating the weekly report along with other information online. 16/05/2020 16/05/2020 Should have done it earlier rather than doing it on the PC and would continue to do it online from hereon to avoid delay.
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Had to re-visit web page basics and also how to create menu’s but managed through. Uploading all the information too some time. 16/05/2020 Taken y

Weekly Progress Report  10

NAME : CHIMI DORJI
PROJECT TITLE  : Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 11 DATE:  22/05/2020
Continue to work on the Final Report.
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Preparing for the Final Report 22/05/2020 22/05/2020 With loads of information selecting the right information is tough .
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Trying to select the most apt resources but finding it challenging and worried might not get the presentation on time. 22/05/2020 Taken y

Weekly Progress Report  11

NAME : CHIMI DORJI
PROJECT TITLE  : Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 12 DATE:  27/05/2020
Was due to Submit the report and the Presentation
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Preparing Report and Presentation 27/05/2020 29/05/2020 Had to finish the Report and presentation by this date 29/05/2020 but unfortunately couldn’t and requested for extension
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Though the report has been completed, voice recording with the presentation is taking some unexpected time 29/05/2020 Taken y

Weekly Progress Report  12

NAME : CHIMI DORJI
PROJECT TITLE  : Edge Computing a way forward for time-critical IoT applications and devices.
WEEK NO : 13 DATE:  03/06/2020
 Submit the report and the Presentation
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT
Submitted Report and Presentation 03/05/2020 29/05/2020 After the requested Extension, have managed to complete the presentation and posted the Final report in the blog
ISSUES
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
The file size was a little off and had to shrink some files 03/06/2020 Taken y