| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 12 | DATE: 29 Jan 2018 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Continue Research project into the future | After exams | TBA | |
| Complete seminar | 29/1/2018 | 27/1/2018 | |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Record presentation | Mon – Fri | Already done | Y |
| Upload presentation to YouTube | Done | Done 27/1/2018 | Y |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Y | |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Difficulty of squeeze in timeframe | Juggled tasks to meet deadline, saved by slack in project timeline | Y | |
Category Archives: Weekly Progress Reports
Weekly Progress Report 11
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 11 | DATE: 22 Jan 2018 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Study week 11 topic | Mon | Mon | all good |
| Research in background | any | Nil | No time, will have to wait until after exams. |
| Work on Presentation | Daily | running behind | Finished 27/1/2018 |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | Watch recording | Y |
| Read topic notes | Mon | Y | |
| Watch topic lecture | Mon | Y | |
| Complete presentation | Daily | working on it | Y |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Y | |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Time frame squeeze | 27/1/2018 | Still balancing tasks to meet deadlines, following illness. | Y |
Weekly Progress Report 10
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 10 | DATE: 15 Jan 2018 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Study week 10 topic | Mon | Mon | all good |
| Research in background | Nil | Nil | issues |
| Online quiz | Done | Done early | Not as good as hoped. |
| Work on presentation | Running late | Not done | |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | Listen recording | Y |
| Read topic notes | Mon | Y | |
| Watch topic lecture | Mon | Y | |
| Study for quiz | Before quiz | Not effective | Y |
| Complete quiz | 8/1/2018 | done 8/1/2018 | Y |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Y | |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Recovering from time squeeze due to illness | Juggling tasks between subjects. Keeping on top of deadlines.
Accepting lower grades, as in risk analysis. |
N | |
Weekly Progress Report 9
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 9 | DATE: 08 Jan 2018 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Study week 9 topic | Mon | Mon | all good |
| Research in background | any | daily | Delayed |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | Listen recording | Y |
| Read topic notes | Mon | Y | |
| Watch topic lecture | Mon | Y | |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Y | |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Running late due to illness and recovery | Had allowed provision for this in slack. | N | |
Weekly Progress Report 8
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 8 | DATE: 01 Jan 2018 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Study week 8 topic | Mon | Mon | all good |
| Complete Annotated bibliography | Mon | Late | see issue |
| Research in background | any | Late | see issue |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | No | N |
| Read topic notes | Mon | No | N |
| Watch topic lecture | Mon | No | N |
| Finish summaries | Sun | N | |
| Finish evaluations | Sun, Mon | N | |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Late | Y |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Sickness prevented work. | 2/1/2018 | special consideration | Y |
Weekly Progress Report 7
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 7 | DATE: 25 Dec 2017 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Break | Until 27th December | ||
| Choose references for annotated bibliography | Dec 28, 2017 | Dec 28, 2017 | No issues, highly organised process. |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Shortlist references | Dec 28, 2017 | done | Y |
| Gather full text | Dec 28, 2017 | done/ using library proxy | Y |
| Read References | Dec 28, 2017 | done | Y |
| Choose references | Dec 28, 2017 | done | Y |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | done | Y |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| No issues | |||
Weekly Progress Report 6
No issues
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 6 | DATE: 18 Dec 2017 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Break | until 27th December | done | |
Weekly Progress Report 5
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 5 | DATE: 11 Dec 2017 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Complete 4 Annotated Bibliography items | Mon – Tues | delayed | Have another assessment due for another subject, need to delay |
| Study week 5 topic | Mon | Mon | all good |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | Listened Tues | Y |
| Read topic notes | Mon | Y | Y |
| Watch topic lecture | Mon | Y | Y |
| Select 4 sources | Mon | Selected 4 sources | Y |
| Write up annotations | Mon – Fri | behind | N |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Y | |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| No issues | |||
Weekly Progress Report 3
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 3 | DATE: 27 Nov 2017 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Study week 3 topic | Mon | Mon | all good |
| Complete Project plan | Mon – Fri | Mon – Fri | big effort, could do with refinement |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | done | Y |
| Read topic notes | Mon | done | Y |
| Watch topic lecture | Mon | done | Y |
| Conceptual Framework | Mon | Running late. Finished Wed | Y |
| Methodology | Tues – Thurs | Unsure if it’s sufficient | Y |
| Deliverables and Risk | Mon – Tues | finished as scheduled | Y |
| References and citations | Mon – Fri | complete | Y |
| Update MS project project | Mon – Fri | all good | Y |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | all good | Y |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Rationale is insufficient | Tues | Complete by week end. | Y |
Weekly Progress Report 2
| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 2 | DATE: 20 Nov 2017 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
|
Complete project plan |
Mon – Fri |
Mon – Sun |
Took longer than scheduled to finish actual MS project |
|
Complete study topic 2 |
Mon – Fri |
Mon – Tues/p> |
no issues/p> |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
|
Watch lecture recording topic 2 |
Mon |
done |
Y |
|
Study topic 2 resources |
Mon – Tue |
done |
Y |
|
Complete sub-tasks of project plan |
Mon – Fri |
finished Sunday |
Y |
|
Update MS project project |
Mon – Fri |
done |
Y |
|
Publish project report |
Mon |
Automatically scheduled |
Y |
|
Update project report |
Mon – Fri |
all good finished Sunday |
Y |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
|
Advanced tables plugin is too time consuming |
Mon |
Replaced plugin tables with plainly coded html tables |
Y |