| NAME: | Yvette Colomb | ||
| PROJECT TITLE: | Possible Android Permission Security Flaw with Google APIs | ||
| WEEK NO: | 11 | DATE: 22 Jan 2018 | |
| PLANNING | |||
| MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
| Study week 11 topic | Mon | Mon | all good |
| Research in background | any | Nil | No time, will have to wait until after exams. |
| Work on Presentation | Daily | running behind | Finished 27/1/2018 |
| TASKS | |||
| DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y/N) |
| Attend chat | Mon | Watch recording | Y |
| Read topic notes | Mon | Y | |
| Watch topic lecture | Mon | Y | |
| Complete presentation | Daily | working on it | Y |
| Publish project report | Mon | Automatically scheduled | Y |
| Update project report | Mon – Fri | Y | |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULTS | FINISHED (Y/N) |
| Time frame squeeze | 27/1/2018 | Still balancing tasks to meet deadlines, following illness. | Y |