Weekly Progress Report 3

NAME:  Yvette Colomb
PROJECT TITLE:  Possible Android Permission Security Flaw with Google APIs
WEEK NO:  3 DATE: 27 Nov 2017
PLANNING
MILESTONE: PLANNED: ACTUAL: COMMENT:
Study week 3 topic Mon Mon all good
Complete Project plan Mon – Fri  Mon – Fri  big effort, could do with refinement
TASKS
DESCRIPTION: DATE: ACTION/RESULTS: FINISHED (Y/N)
Attend chat Mon  done  Y
Read topic notes Mon  done  Y
Watch topic lecture Mon  done  Y
Conceptual Framework Mon  Running late. Finished Wed  Y
Methodology Tues – Thurs  Unsure if it’s sufficient  Y
Deliverables and Risk Mon – Tues  finished as scheduled  Y
References and citations Mon – Fri  complete  Y
Update MS project project Mon – Fri  all good  Y
Publish project report Mon Automatically scheduled Y
Update project report Mon – Fri  all good  Y
ISSUES
DESCRIPTION DATE ACTION/RESULTS FINISHED (Y/N)
Rationale is insufficient  Tues  Complete by week end.  Y