WEEK NO: | 04 | DATE: | 22-03-2021 |
---|---|---|---|
PLANNING | Completing the Assignment 2 | ||
MILESTONE: | PLANNED: | ACTUAL: | COMMENT: |
completing the project proposal on time | -Complete the project plan and proposal -Submit to turnitin | Completed the assignment 2 on time and submitted to turnitin. | success |
ISSUES | |||
DESCRIPTION: | DATE: | ACTION/RESULTS: | FINISHED (Y?N) |
turnitin score was over 15% | 21-03-2021 | Was able to reduce the score by doing more paraphrasing | Y |