Week 2 Progress Report
After the selection of topic, In second week I started working on blog setup and updated my blog with intro, weekly report content and prepared an abstract for the submission.
| NAME | SUNIL RAJ SHRESTHA | ||
| PROJECT TITLE | BIOMETRICS AUTHENTICATION | ||
| WEEK NO | 2 | DATE | 27/07/2020 |
| PLANNING | |||
| MILESTONE | PLANNED | ACTUAL | COMMENT |
| Finalizing Research Topic, Abstract and Blog Setup | 29/07/2020 | 30/07/2020 | Created blog using CSU Thinkspace. Added content to blog such as About Me, Weekly Report, Project Summary etc. |
| Update weekly progress | 29/07/2020 | 31/07/2020 | Update week 2 progress report |
| ISSUES | |||
| DESCRIPTION | DATE | ACTION/RESULT | FINISHED (Y/N) |
| – | – | – | Y |