PROJECT WEEK 05 BLOG

 STAGE 2 RESEARCH TASK 1:

Name: Dishali khilari
Project Title: Dishali’s Organic farm fertiliser based on IoT and Automation Project.
Week No: 05 Date :        13/04/2020
Planning: Approach of Researches.
Milestone Planned: Actual: Comments:
Researching number of different journal and article for annotated bibliography and Sources to be used. 29/4/2020 To be done. Gathering all the information from the right resource and using the right paper which is applicable for my project.
Issues: The only problem found was not a specific paper or journal found to gather information.
Description:  Date: Action Done/ Result: Finished(Yes/No)
The information which will be needed for next task like Annotated Bibliography. 7/4/2020 Research is done with the help of project planning and with the required information needed. Yes