Project Plan

Duration

The project is scheduled to run from the start of Charles Sturt University Session 2 2020 on 6 July 2020. The final deliverable for the project is due on 6 October 2020.

Deliverables

This Project includes the deliverables listed within Table 1 to be provided on or before the due dates, unless coordinated through the Charles Sturt University assessment extension process:

IDDeliverableDue Date
A1.1Project Title, Abstract, and Blog Website26 July 2020
A1.2Collated Weekly Progress Reports6 October 2020
A2.1Project Proposal and Plan10 August 2020
A3.1Annotated Bibliography14 September 2020
A3.2Journal Synopsis14 September 2020
A4.1Final Report6 October 2020
A4.2Recorded Presentation6 October 2020
Project Deliverables

Work Breakdown Structure

Gantt Chart